CNG vehicle refueling stations supply CNG and meter it, both handled by CNG dispensers. Each dispenser is connected to a gas intake pipe (with a metering device inside) and a refueling hose and nozzle (or spout) at the end. Each dispenser should have its own or be equipped with a disconnect valve for connection to the refueling hose.

1. CNG Dispenser Process Flow

The CNG refueling process flow varies slightly depending on the gas intake pipe system. When the number of dispensers is small, such as 1-3 units, a single-pipe intake system can be used, where each dispenser is connected to a corresponding gas intake pipe. The simplest single-pipe intake refueling process flow is as follows: after connecting to the gas intake pipe (including the refueling valve, pressure gauge, and pressure relief valve), connect the disconnect valve, refueling hose, and nozzle in sequence. This simple process is only suitable for internal enterprise use. When there are three or more CNG refueling stations, a multi-pipe gas intake system is often used. Each refueling station connects to its respective tiered gas intake interface, drawing gas from the main gas intake pipes. Natural gas flows through the internal gas intake control valve group (sequential control panel) of the refueling station, sequentially passing through the mass flow meter, the main gas intake valve, the disconnect valve, the refueling hose, and the refueling nozzle to refuel CNG vehicles. The number of intake pipes is set accordingly.

CNG vehicle refueling stations often use a three-pipe gas intake process.

The three-pipe gas intake process flow for multiple refueling stations in parallel is shown in the figure. The two-pipe gas intake process reduces one main intake pipe and its corresponding branch pipe from the three-pipe system. If a separate compressor direct-fill pipe needs to be added to the three-pipe system, the refueling station must be configured with corresponding connecting pipes. After refueling, the natural gas released from the high-pressure refueling hose can be recovered through the pressure-relief return pipe or released centrally in accordance with regulations.

Parallel Process Flow of Three-Stage Three (Four) Dispensers

2. CNG Refueling Station Process Flow

CNG refueling stations can be classified into fixed refueling stations and mobile refueling stations based on their overall mobility.

Fixed Refueling Station

The functions of a fixed CNG refueling station include unloading, compression, storage, and refueling. Its process flow is as follows: After the CNG transport vehicle enters the station and connects to the unloading column, CNG is supplied to the CNG refueling station via three routes.

One route replenishes CNG to the low-pressure stage storage equipment in the storage facility via a priority/sequence control panel.

Another route, when the pressure inside the transport vehicle decreases and cannot be replenished, uses a compressor to pressurize the CNG and supply it to the storage equipment.

The third route treats the transport vehicle (CNG container) as a set of “storage equipment” within the station from the beginning, directly participating in the refueling of CNG vehicles via a sequence control panel.

LCNG vehicle refueling stations

The CNG pressurized by the compressor is stored in the storage facility as required by the storage priority control panel.

When the gas storage facility has a small volume, a two-stage gas storage system can be used, meaning the station’s gas cylinder group has only high- and medium-pressure stages, with the low-pressure stage handled by the tube bundle trailer used for unloading at the site. For larger systems, a three-stage gas storage system can be used. When CNG vehicles need refueling, the refueling machine draws gas from the lower-level storage unit via a single-pipe gas intake manifold and a gas intake sequence control panel, and then begins refueling. When the pressure falls below a set value, the gas intake sequence control panel switches to a higher-level storage unit until refueling is complete. When the pressure in the highest-level storage unit falls below a set value (e.g., 22 MPa), the compressor starts, draws gas from the CNG transport vehicle’s storage container, pressurizes it, and directly refuels the CNG vehicle. Simultaneously, the gas storage facility is also replenished. The CNG refueling process follows a pre-set storage schedule, controlled by a priority storage control panel, until the CNG transport vehicle’s storage container is completely emptied (down to the set minimum pressure). The CNG transport vehicle then returns to the refueling station (mother station) for refueling.

The refueling equipment at CNG refueling substations typically uses small reciprocating compressors

Which can be driven by an electric motor or hydraulically. Hydraulically driven compressors use a screw pump to compress lubricating oil, generating power to drive the piston movement of the reciprocating compressor to complete the compression task. These compressors have a smaller displacement but are lighter, easier to move, and quieter. For stationary refueling substations, the compression and storage equipment can also be the aforementioned storage column with a liquid pump. Depending on the needs of the control instruments and actuators, an air compressor system may also be installed as the control power system.

CNG refueling substations

Bluesky Energy uses a hydraulically driven compressor in its CNG substation solutions, offering high integration and rapid station construction. It is suitable for various substation scenarios. With a built-in dual hydraulic drive system, only half of the system needs to be activated when the station load is low, resulting in higher economic efficiency. It is highly adaptable to various scenarios and needs.

CNG compression station pressure regulation and metering