How to ensure the smooth operation of LCNG refueling station?

Bluesky Natural Gas’s after-sales team provided the LCNG refueling station commission for our Nigerian customer in Kano in April 2026. This station was purchased at the end of 2024, but it did not start running until May of 2026.

Previously, we thought this station could start operating in June 2025, but it was delayed by more than 10 months due to the customer’s unclear plan. This also causes customers to lose profits and allows other competitors to enter the market.

LCNG gas station in Nigeria

1. Civil Work

Normally, our LCNG equipment will need around 35 days for production. During this time, we can provide customers with equipment basement drawing, and guide customer to do the adjustment for their station drawing, like :

  • The basement of the LNG storage tank should be a certain height higher than the L-CNG pump skid.
  • The suggested distance between different types of equipment.
  • The suggested place for the LCNG vaporizer, that part of the vaporizer will have some ice appear, and also cause a large amount of white mist. It will require being far away from the refilling system, and so on. Of course, Bluesky can provide customers with full station drawings, including work and installation processes. The customer could start this part during production and shipping.

The LCNG gas station is under installation.

2. Equipment and pipeline installation :

The customer should find an experienced installation team that has already completed the exact project.

The customer first hired the local team for this station. This delayed the installation, and the installation team leader purchased many unnecessary spare parts.

In the end, the customer chose our Chinese installation team for their station and finished the installation work in two weeks.

LCNG refueling station

3. Equipment commission :

Before the LCNG refueling station starts operating, we need to use a cryogenic liquid to cool the LNG storage tank and LNG pipeline(normally liquid nitrogen). And should unload the LNG for this station in one month. Otherwise, the increased temperature of the equipment will gasify the LNG and waste.

Bluesky mentioned this before arriving, but the customer did not confirm it until our team arrived at the station. And the LNG was obtained after two weeks. This increases the customer’s cost for commission work. And also delayed the running date of the LCNG station.

The LCNG gas station is currently undergoing commissioning.

According to the above situation, the customer has made mistakes at every stage, causing this significant delay in the opening date of this LCNG station. The first time we visit this city, we find that it is the first LCNG station. But now that other companies are opening LCNG stations around and providing CNG for the drivers.

Avoiding these mistakes can help you enter the market and start the business quickly.