Today I’d like to talk about the company’s installation of an LCNG station for Jamaican customers.
Services provided by Blue Sky Energy to its Jamaican client:

- The entire station equipment was provided by Blue Sky Energy, including one LNG unloading skid, two 60m³ storage tanks, two LCNG pump skids, two LCNG vaporizers, two CNG tube group, four double nozzle CNG dispensers, a PLC control cabinet, a power supply cabinet, CNG leakage detection systems, and all valves, piping, and cables for the station.
- Blue Sky Energy provided the station’s design drawings, which included the civil engineering, equipment, and piping layout, valve installation methods, electrical connection methods, piping welding requirements, and the required on-site installation materials.

- After-sales personnel provided on-site installation guidance, on-site commissioning, and employee training services.
- Equipment Installation Process: This station is an LCNG station, using LNG as its gas source and CNG for refueling. This means that the upstream equipment, pipelines, and valves must withstand cryogenic temperatures (LNG’s temperature is -162℃), while the downstream pipelines must operate at high pressure (CNG’s operating pressure is 20MPa~23MPa). Since CNG is a flammable gas, the entire station requires leak and pressure tests to ensure there are no gas leaks.
- Equipment Commissioning Process: Liquid nitrogen is used to simulate LNG operation. The LNG storage tank is pre-cooled with liquid nitrogen (because the gas inside the LNG tank is at room temperature during transportation; directly adding cryogenic liquid would cause rapid vaporization and excessive pressure inside the tank). Liquid nitrogen is unloaded into the LNG storage tank using an unloading skid, pressurized to 23MPa using an LCNG pump skid, and then vaporized into nitrogen in the LCNG vaporizer. This nitrogen is then sequentially fed into the CNG tube group via a sequence control panel and finally refueled using a CNG dispenser.

Problems occurred during installation and on-site solutions:
Significant discrepancies between on-site infrastructure and blueprints
Problem: The client did not follow the design drawings for civil construction, omitting the trenches for pipes and cables. This necessitated a redesign of the ground pipe and cable layout, increasing the amount of installation materials required, increasing the installation costs, and delaying the completion date.
Cause: The client only considered civil construction costs, neglecting the resulting installation problems and increased costs. And they haven’t notified the installation team earlier, leading to the problem being discovered only upon their arrival on-site.
Solutions: Emergency design revisions, re-estimation of installation materials, and immediate arrangement for material transportation.

Jamaica is short of industrial, building, and installation materials.
Problem: Missing pressure pipes, cables, and connectors cannot be purchased locally. Other materials are 5-10 times more expensive than in China, resulting in extremely slow on-site installation progress.
Causes: Jamaica has scarce local resources and relies mainly on tourism for growth, with limited industrial capacity.
Solutions: Arranged express freight from China, and also the installation team purchased the short materials in the US market. However, this also drastically increased costs, and the extremely low customs clearance efficiency in Jamaica (7 days for air freight, 14 days for customs clearance) further extended the installation time.

Lessons and Lessons Learned:
- Do market research for the project country before material transportation. Consider the difficulty of purchasing the emergency materials.
- Confirm the on-site construction situation before the installation team arrives. The cost of overseas personnel being present is extremely high. Make sure no unnecessary expenses happened.
- Ensure sufficient spare installation materials to avoid material shortages due to transportation damage or last-minute changes to the installation plan.