Several seemingly ordinary details often determine the operating condition of a gas generator set: whether the engine fluid levels, including oil and coolant, are sufficient; whether the battery system is reliable; and whether the startup/shutdown procedures are properly followed.
Spending a few extra minutes on inspection before startup is usually much more efficient than stopping the unit during operation to troubleshoot and repair faults.
This document summarizes the most commonly overlooked points during daily operation, providing a useful checklist for operators to follow.
The load ratio, methane concentration of the gas supply, and maintenance intervals mentioned in this document are recommended reference values only. Requirements may differ based on different brands, power ratings, and fuel supply solutions (such as natural gas or CNG systems).
If there is any inconsistency between this document and the equipment nameplate, controller settings, manufacturer manuals, or site safety management procedures, the manufacturer’s documents and on-site safety regulations shall prevail.

Pre-Startup Inspection
Pre-startup inspection is not simply a matter of “taking a quick look.” Operators are advised to check each system systematically, including the gas supply system, lubrication system, cooling system, and electrical system, before starting the generator set.
If any gas leakage, insufficient fluid level, loose wiring connection, or controller alarm is detected, the issue must be resolved first. Do not attempt repeated startups to bypass or conceal potential faults temporarily.
| Inspection System | Key Inspection Points | Principles for Handling Abnormal Conditions |
| Gas Supply System | No leakage from gas pipelines, joints, valves, or flexible connections; valves are in the correct position; gas supply pressure meets equipment requirements and remains relatively stable. | If a gas smell is detected, gas leakage noise is heard, or gas pressure is obviously unstable, do not start the generator set. Close the relevant valves, ventilate the area, and report the issue for repair. |
| Lubrication System | Engine oil level is between the upper and lower marks on the dipstick. Use the specified 15W-40 engine oil. There should be no obvious oil leakage around the oil pan or oil filter. | Starting the unit with insufficient engine oil is strictly prohibited. After adding oil, recheck the oil level. If the oil level repeatedly drops, investigate the cause of oil leakage. |
| Cooling System | Coolant level is normal; there is no obvious blockage on the radiator surface; the fan and belt are in good condition; ventilation passages around the generator set are unobstructed. | If the coolant level is insufficient, the radiator is blocked, or the fan is abnormal, resolve the issue before startup. Do not operate the generator set with existing faults. |
| Electrical System | Battery voltage and wiring are normal. Battery terminals are free from looseness or corrosion. The controller, emergency stop circuit, and protection devices show no alarms. | If alarms have not been cleared, terminals are overheating, or the starting power supply is insufficient, do not repeatedly attempt to start the unit. Check the power supply and control circuit first. |
Table 1: Basic Four-System Inspection Before Startup
Startup Instructions
Before operating the generator set, confirm that no personnel are performing maintenance work on site and that there are no open flames or obvious gas leaks in the gas area. Then open the gas valve according to the equipment operating procedures.
After opening the gas valve, first observe whether the gas supply is stable. Confirm that there is no abnormal gas odor, significant pressure fluctuation, or alarm indication before proceeding with the startup operation.
During startup, do not keep cranking the starter motor for an extended period in an attempt to achieve a successful start on the first try. The generator set should not be started more than three times continuously, and each startup attempt should have an interval of at least 30 seconds. If the unit still fails to start after three attempts, investigate the cause, including issues related to the gas supply system, electrical system, ignition system, or control system.
After the generator set starts, allow the engine speed to gradually stabilize before verifying the critical operating parameters. Temporary fluctuations immediately after startup do not necessarily indicate a fault. However, if the engine oil pressure fails to build up within the expected time, engine speed fluctuates significantly, abnormal exhaust conditions occur, or unusual knocking sounds are detected, shut down the unit immediately for inspection.
Upon confirmation that the voltage and frequency are stable and that no new alarms are displayed by the protection system, the generator set should be gradually connected to the load.
| Observation Items After Startup | Normal Observation Criteria | Situations Requiring Special Attention |
| Engine Oil Pressure | The oil pressure should be established within a short period after startup and remain stable. The specific value shall comply with the manufacturer’s requirements. | Continuous low oil pressure, sudden pressure drop, or mechanical abnormal noise occurring at the same time. Shut down the generator set immediately. |
| Engine Speed (RPM) | Engine speed should gradually increase to the rated speed without obvious fluctuations during operation. | Unstable engine speed, frequent fluctuations, or abnormal response from the speed governor. |
| Voltage and Frequency | Voltage and frequency should be established gradually after startup and stabilize in accordance with the generator set’s rated parameters. | Voltage too low/high, significant frequency deviation, or activation of protection devices. |
| Noise, Vibration, and Exhaust Condition | Operating sound should be uniform, vibration should remain within the allowable range of the equipment, and there should be no obvious abnormal exhaust color or odor. | Backfire, explosion-like knocking sounds, metallic impact noises, severe vibration, or continuous black smoke emission. |
Table 2 First-Minute Checks After Equipment Startup

Precautions During Operation
Maintain Stable Load Control
During the break-in period of a new generator set, it is recommended to keep the load between 50%-80% for the first 50 hours, giving adequate time for the engine, generator, and thermal management system to achieve stable running conditions. During long-term operation, the load should generally be maintained at 60%-85%. The actual load should also be adjusted according to the ambient temperature, altitude, gas calorific value, and rated capacity of the generator set. Load adjustment should be carried out gradually to avoid instantaneous impact caused by starting high-power equipment at the same time.
Long-term operation at a load below 30% may result in incomplete combustion, low exhaust temperature, and excessive carbon accumulation. In the long term, exhaust smoke or unstable ignition. If the actual power demand at the site is relatively low, periodic load operation or adjustment of the generator set configuration should be arranged according to the manufacturer’s recommendations. Do not simply rely on “running at no load for a longer time” as a substitute for maintenance.
Gas Quality and Gas Supply Conditions
The methane concentration of natural gas is recommended to be no lower than 85%. The gas should not contain excessive moisture, oil contamination, or solid particles. When impurities enter the pressure regulator, mixer, or ignition components, they may cause unstable gas supply, poor combustion, and component wear.
When using CNG as the gas supply, attention should also be paid to the condition of the pressure reduction equipment and filters. If abnormal frosting, pressure fluctuations, or pipeline vibration are found, the load should be reduced immediately, and the system should be inspected.
During operation, do not arbitrarily adjust the gas pressure regulation, air-fuel ratio, or controller parameters. Even slight parameter adjustments may affect combustion temperature and power generation stability. When adjustment is required, it should be carried out by professional personnel familiar with the generator set and gas system according to the manufacturer’s procedures, and adjustment records should be maintained.
Temperature, Ventilation, and Environment
A gradual increase in temperature, frequent fluctuations, or abnormally high temperature under low load conditions should be taken seriously. During inspection, the radiator, fan, belt, coolant level, and ventilation conditions of the generator room should be considered comprehensively.
Flammable materials must not be stored in the generator room. Air inlets and exhaust outlets must not be blocked by external objects. The exhaust pipe and its surrounding area should maintain sufficient protective distance.
Anti-Backfire and Explosion Prevention
During generator operation, it is strictly prohibited to disassemble the intake pipeline, filter, or mixer. Hot work, affecting operations, and welding near gas pipelines are also prohibited.
If a CNG generator set experiences backfire, popping sounds, abnormal noises, increased gas odor, or other abnormal conditions, immediately unload the generator, shut down the unit, close the gas valve, eliminate possible ignition sources, and notify maintenance personnel for handling.
Shutdown Precautions
During normal shutdown, gradually reduce the load first, enabling the generator set to operate under light load or no-load conditions for a short period of time. This allows the temperature and lubrication conditions to stabilize before pressing the shutdown button on the controller.
After shutdown, confirm that the engine speed has reduced to zero and that there are no abnormal residual noises. Then close the gas valve and related power supplies according to site operating requirements.
If the equipment is equipped with an automatic idle shutdown program, allow the program to complete its full sequence. Do not directly cut off the gas supply while the engine is still operating at high temperature or high speed.
Emergency shutdown should only be used in situations such as:
- Gas leakage;
- Backfire;
- Severe overheating;
- Extremely low engine oil pressure;
- Severe vibration;
- Threats to personnel safety.
After an emergency shutdown, do not restart the generator set immediately.
Maintenance Schedule Guidelines
Under the following conditions:
- High dust environments;
- Unstable gas quality;
- Frequent startup and shutdown cycles;
- Long-term high-load operation;
- Parts including air filters, spark plugs, engine oil, and other consumable parts may require inspection or replacement.
Each maintenance activity should be properly recorded, including:
- Operating hours;
- Replacement materials used;
- Problems identified;
- Corrective actions taken.
| Maintenance Items | Recommended Interval | Maintenance Focus |
| Engine Oil and Oil Filter | 300 hours | Check oil condition and inspect for metal particles or emulsification. Replace engine oil and oil filter according to requirements, then confirm oil level and check for leakage after replacement. |
| Air Filter | Inspection at 500 hours; replacement at 1,000 hours | Shorten inspection intervals in dusty environments. A clogged filter will reduce intake air flow and affect combustion performance. Do not continue operation with a damaged air filter. |
| Spark Plugs | Inspection at 500 hours; replacement at 1,000-1200 hours | Check electrode wear, carbon deposits, and spark plug gap. Replace earlier if cracks are found on the ceramic insulator or if ignition performance becomes unstable. |
| High-Voltage Ignition Coil | Inspection at 2000-4000 hours | Monitor insulation condition, connectors, and ignition energy performance. If misfire or poor ignition occurs, carry out troubleshooting and inspection in advance. |
| Valve Clearance | Inspection at 2000-2500 hours | Inspection and adjustment shall be performed by qualified personnel familiar with engine structures according to the manufacturer’s cold or hot adjustment requirements, and all results should be recorded. |
| Major Overhaul | About 30000 hours | Evaluate the overhaul requirement based on compression pressure, engine oil consumption, exhaust condition, vibration levels, and fault records. The specific overhaul standard shall follow the manufacturer’s requirements. |
Table 3 Recommended Maintenance Intervals and Key Site Inspection Points

Principles for Handling Abnormal Conditions
The general sequence is: stop loading or press the shutdown button, close the gas valve, maintain ventilation in the generator room, place a warning area, and notify maintenance personnel. Without confirmation, repeated ignition attempts, forced resetting of protection devices, or disassembly of gas pipelines are not allowed.
During daily operation, operators can develop the habit of “listening to sounds, checking instruments, smelling odors, and reviewing records.” Timely handling of minor problems can often prevent them from developing into shutdown accidents. During each shift handover, the current load, gas supply condition, latest maintenance time, and issues requiring continued attention should be clearly explained.
Note: This document is intended for daily operation reminders and does not replace equipment manuals, gas station operating procedures, fire protection requirements, or maintenance work permit systems.